The Stats
Location: Gray, Texas
Nameplate Capacity: 200MW
Construction Cost Estimates: $300,000,000
In Service Date: Spring 2013
Total Acreage: 16.000
Average Wind Speed: 8.3 m/s @ 85m
Expected Capacity Factor: 40%
Power Market: ERCOT
Checking in on the Progress
Met Towers Installed: 1
Years of Data Collection Began: 2007
Wind Study: In Progress
Permitting: In Progress
Power Purchase Agreement: Negotiating
Transmission Interconnect: Impact Study Phase
Zoning: In Progress