Haynes

The Stats

Location: Gray, Texas

Nameplate Capacity: 200MW

Construction Cost Estimates: $300,000,000

In Service Date: Spring 2013

Total Acreage: 16.000

Average Wind Speed: 8.3 m/s @ 85m

Expected Capacity Factor: 40%

Power Market: ERCOT

Checking in on the Progress

Met Towers Installed: 1

Years of Data Collection Began: 2007

Wind Study: In Progress

Permitting: In Progress

Power Purchase Agreement: Negotiating

Transmission Interconnect: Impact Study Phase

Zoning: In Progress